Task 1. draw AON network Task 2. calculate critical path Task 3. Assess the probability of finishing within 22 days Activity m a b Predecessor A 54 6 13 A(FS2) C 7410 A(FS3) D 5 37 B(FS2),C(FFo) E 4 3 5 D(FSo)” aria-describedby=”ht9″>
Assignment . A project data is shown as table >Task 1. draw AON network Task 2. calculate critical path Task 3. Assess the probability of finishing within 22 days Activity m a b Predecessor A 54 6 13 A(FS2) C 7410 A(FS3) D 5 37 B(FS2),C(FFo) E 4 3 5 D(FSo)