Determine the total project completion time and the critical path for the project
McGee Carpet and Trim installs carpets in commercial offices. Andrea McGee has been very concerned with the amount of time it took to complete several recent jobs. Some of her workers are very unreliable. A list of activities and their optimistic completion time, the most likely completion time, and the pessimistic completion time (all in days) for a new contract are provided in a given table. Following are the activities that are required to install the carpets in the offices:
Activity 1: Measure office room dimensions
Activity 2: Estimate cost
Activity 3: Material requisition
Activity 4: Workforce requisition
Activity 5: Special tool requisition
Activity 6: Installation
Activity 7: Inspection and customer acceptance
Activity 2 starts immediately after Activity 1. Activity 3, Activity 4, and Activity 5 start concurrently after Activity 2. Activity 6 does not start until after Activity 3, Activity 4, and Activity 5 are completed. The carpet installation project is complete after Activity 7 is completed. If OT = Optimistic Time, MT = Most Likely Time, and PT = Pessimistic Time, use a Program Evaluation Review Estimate (PERT) to compute the statistical time for each activity, as in the following table:
Activities
OT
MT
PT
Activity 1
2
3
4
Activity 2
3
6
9
Activity 3
4
8
12
Activity 4
6
8
10
Activity 5
8
10
12
Activity 6
10
14
18
Activity 7
4
6
8
You must also do the following:
Determine the expected completion time and the variance for each activity
Determine the total project completion time and the critical path for the project
Determine Early Start (ES), Early Finish (EF), Late Start (LS), and slack for each activity
What is the probability that McGee Carpet and Trim will finish the project in 40 days or less?
Define project management and the necessary requirements.
Analyze implications of changes in project scheduling.
Evaluate application of project management techniques in terms of the firm’s business operational goals and requirements.
Please submit your assignment in an APA-formatted paper.
Submitting your assignment in APA format means, at a minimum, you will need the following:
Title page: Remember the running head. The title should be in all capitals.
Body: The body of your paper begins on the page following the title page and abstract page and must be double-spaced (be careful not to triple- or quadruple-space between paragraphs). The type face should be 12-pt. Times Roman or 12-pt. Courier in regular black type. Do not use color, bold type, or italics except as required for APA-level headings and references. The deliverable length of the body of your paper for this assignment is 2–3 pages. In-body academic citations to support your decisions and analysis are required. A variety of academic sources is encouraged.
Reference page: References that align with your in-body academic sources are listed on the final page of your paper. The references must be in APA format using appropriate spacing, hang indention, italics, and upper- and lowercase usage as appropriate for the type of resource used. Remember, the Reference Page is not a bibliography but a further listing of the abbreviated in-body citations used in the paper. Every referenced item must have a corresponding in-body citation.
. WITH nursing Writers TODAY AND GET AN AMAZING DISCOUNT
The post Determine the total project completion time and the critical path for the project appeared first on nursing Writers .
“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”

The post Determine the total project completion time and the critical path for the project appeared first on nursing Writers.
Determine the total project completion time and the critical path for the project was first posted on July 30, 2019 at 5:44 am.
©2019 "Nursing Paper Tutors". Use of this feed is for personal non-commercial use only. If you are not reading this article in your feed reader, then the site is guilty of copyright infringement. Please contact me at support@classassignmenthelp.com
Source link
“Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!”

Determine the total project completion time and the critical path for the project was first posted on July 30, 2019 at 5:46 am.
©2019 "nursing Writers". Use of this feed is for personal non-commercial use only. If you are not reading this article in your feed reader, then the site is guilty of copyright infringement. Please contact me at admin@classassignmenthelp.com
"Is this question part of your assignment? We Can Help!"
Determine the total project completion time and the critical path for the project was first posted on July 30, 2019 at 5:47 am.